St. Mary’s Hospital Par Excellence System

This project was a 15-phase project completed within a 6-month timeframe. The work consisted of remodeling 46 rooms ranging from ICU, ED, NICU, Central Sterile to OR. Par Excellence Panels were installed to help the Hospital keep inventory of products used throughout the entire facility. Each phase consisted of 2-4 rooms in different areas to eliminate as much disruption as possible to the Hospital. PNCI was able to successfully keep ICRA containment and ISLM’s up to date and maintain a zero incident. The project completed on schedule due to a team who specializes in Hospital Construction and maintained constant communication with staff and management.